Manfacturing Facility February Progress

With the build of Thorpe's new HQ entering it's second month progress has shown no signs of slowing. After fully levelling the ground and ensuring the requisite stability work could begin on the framework.

Following the drilling and filling of the foundations the installation of the steel framework began to take shape very quickly, with much of the front section completed in just under two days. The frame erection teams have worked exceptionally hard to ensure that progress was not stalled despite the attentions of Storm Doris and as February came to a close we can see the build starting to resemble the vision laid out in our designs.